Excavation, embankment and earthwork states
Earthwork volumes between cross-sections are computed by the average-end-area method, V = [(A1 + A2)/2] × L. Soil changes volume as it is handled: excavated bank material swells when loosened for haul and shrinks when compacted into embankment, so a balance drawn in one state must be converted before it is compared in another. Exam questions name the state — bank, loose or compacted cubic yards — and the conversion direction is the whole question.
V = [(A1 + A2)/2] × L · Loose volume = bank volume × (1 + swell)
Worked example Average-end-area volume with swell
Given: Two sections 100 ft apart have cut areas of 200 ft² and 300 ft². Find the bank volume, and the loose volume at 25% swell.
Solution:
- V = [(200 + 300)/2] × 100 = 250 × 100 = 25,000 ft³.
- Bank yards: 25,000/27 = 926 yd³.
- Loose: 926 × 1.25 = 1,157 yd³.
Answer: Bank volume ≈ 926 yd³; loose volume ≈ 1,157 yd³.
Layout, control and curve elements
Site layout sets the work from control points, and horizontal curves carry alignments around corners. For a circular curve, the degree of curve D ties to radius by R = 5,729.58/D (arc definition, feet), the tangent length is T = R tan(Δ/2), and the curve length is L = RΔ with Δ in radians — equivalently L = 100Δ/D in feet. The PC, PI and PT anchor every layout question: tangent in, curve, tangent out.
R = 5,729.58/D · T = R tan(Δ/2) · L = 100Δ/D
Worked example Curve elements
Given: A horizontal curve has degree of curve D = 10° and intersection angle Δ = 40°. Find R, L and T.
Solution:
- R = 5,729.58/10 = 573 ft.
- L = 100 × 40/10 = 400 ft.
- T = 573 × tan(20°) = 573 × 0.364 = 208.5 ft.
Answer: R ≈ 573 ft; L = 400 ft; T ≈ 209 ft.
Erosion control, retaining walls and safety
Erosion and sediment control keeps soil on the site: silt fence and check dams slow and pond runoff, stabilisation covers exposed soil, and controls are inspected and maintained — a silt fence is a sediment control, not an erosion control, a distinction the exam draws. Retaining walls are checked for sliding (friction resistance against the earth-pressure resultant) and overturning, each with its factor of safety. Safety duties centre on excavation protection: sloping, benching, shoring or shielding, with the flattest slopes for the weakest (Type C) soils.
FSsliding = μW / Pa · Pa = ½ Ka γ H²
Worked example Sliding check for a retaining wall
Given: A wall weighing 10,000 lb per foot of length sits on soil with friction coefficient μ = 0.50. The retained soil (γ = 120 lb/ft³, Ka = 0.333) stands 10 ft high. Find the sliding factor of safety.
Solution:
- Resultant thrust: Pa = ½ × 0.333 × 120 × 10² = 2,000 lb/ft.
- Friction resistance: 0.50 × 10,000 = 5,000 lb/ft.
- FS = 5,000/2,000 = 2.5.
Answer: Sliding FS = 2.5.